Additional Central Assistance Release Status,
From 01-Apr-2002 To 03-Feb-2012
Additional Central Assistance -> West Bengal -> CMC-WB-Calcutta Municipal Corporation
(Amount in INR) राशि (रुपये में)
Project Id
of which Additional Central Assistance Component
Recommended
Cash Release
Book Adjustment
1813-IND - Calcutta Environmental Improvement Project6,281,013,200 1,263,066,000 5,017,947,200 
FRGL4201 - FF-105 Million Pt. dt.23.11.98,CMC-WB,LA-124,746,000 24,746,000 
FRGL4201E - FF-105 Million Pt. dt.23.11.98,CMC-WB,LA-1126,639,000 126,639,000 
P-362-IN - Calcutta Water Supply Sewerage And Drainage Project9,099,000 3,631,000 5,468,000 
UKGG024 - Calcutta Slum Improvment Project7,126,000 7,126,000 
Total
कुल
6,448,623,200 1,273,823,000 5,174,800,200